Which of the following best describes an increment of working software?

 
 
 
 
 

What are three benefits of self-organization?

 
 
 
 
 

Which two things are appropriate for a Scrum Master to do if the Development Team doesn’t have the engineering tools and infrastructure to completely finish each selected Product Backlog item?

 
 
 
 
 

When a Development Team is having trouble delivering a working lncrement because they don’t understand a functional requirement, what should they do?

 
 
 
 

How much work must a Development Team do to a Product Backlog item it selects for a Sprint?

 
 
 
 

Who owns the Sprint Backlog?

 
 
 
 

When do Development Team members take ownership of a Sprint Backlog item?

 
 
 
 

Which outcome is expeeted as Scrum Teams mature?

 
 
 
 
 

The definitions of “Done” is used to:
(Choose three answers)

 
 
 
 
 

The purpose of a Sprint is to produce a done increment of Product.

 
 

The product Owner must release each increment to production.

 
 
 
 

Who creates a Product Backlog item’s estimate?

 
 
 
 
 

When is a Sprint over?

 
 
 
 

How often should Development Team membership change?

 
 
 
 

When does the next Sprint Planning?

 
 
 
 

When can a Development Team cancel a Sprint?

 
 
 
 
 

Choose three responsibilities of a self-organizing Development Team.
(Choose three answers)

 
 
 
 
 
 

Which three questions are answered by all Development Team members at Dally Scrum?

 
 
 
 
 

Which of the following might the Scrum Team discuss during a Sprint Retrospective?

 
 
 
 
 

An organization has decided to adopt Scrum, but management wants to change the terminology to fit with terminology already used. What willlikely happen if is done?

 
 
 
 

If burndown charts are used to visualize progress, what do they track?

 
 
 
 

A Scrum Master is keeping a list of open impediments, but It is growing and he/she has been able to resolve only a small portien of the impediments. Which three (3) techniques would be most helpful in this situation?
(Choose three answers)

 
 
 
 
 
 

Which statement best describes the Sprint Backlog as outcome of the Sprint Planning?

 
 
 
 
 

Which of the following are roles on Scrum Team?
(Choose all that apply)

 
 
 
 
 

A Scrum Master is keeping a list of open impediments, but I is growing and he/she has been able to resolve only a small portien of the impediments. Which three (3) techniques would be most helpful in this situation?
(Choose three answers)

 
 
 
 
 
 

Which are NOT appropriate topics for discussion in a Sprint Retrospective?
(Choose 2 answers)

 
 
 
 
 

What does it mean for a Development Team to be cross-functional?

 
 
 
 

Who is responsible for clearly expressing Product Backlog Items?

 
 
 
 

What is time-box for the Sprint Review?

 
 
 
 
 

If two Scrum Teams are added to the development of a product that previously had only one Scrum Team, what will be immediate impact on the productivity of the original Scrum Team?

 
 
 

A product increment must be released to production at the end of each Sprint.

 
 

Who must do all the work to make sure Product Backlog items conform to the definition of “Done?”

 
 
 
 
 

How should a development team deal with non-functional requirements?

 
 
 
 

A Scrum Master is working with a Development Team that has members in different physical locations. The Development Team meets in a variety of meeting rooms and has much to do logistically (for example, set up conference calls) before the Daily Scrum. What action should the Scrum Master take?

 
 
 
 

A product increment must be released to production at the end of each Sprint.

 
 

The purpose of a Sprint is to produce a done increment of Product.

 
 

The Daily Scrum is an event that happens every day. What would be three key concerns if the frequency were to be lowered to every two or three days?
(Choose the best three answers)

 
 
 
 
 
 

The time-box for a Daly Scrum is?

 
 
 
 
 

When multiple teams are working together on the same product, each team should maintain a separate Product Backlog.

 
 

Who determines how work is performed during the sprint?

 
 
 
 
 

During a Sprint Retrospective, the Development Team proposes moving the Daily Scrum to only occur on Tuesdays and Thursdays. Which two are the most appropiate responses for the Scrum Master?
(Choose the best two answers)

 
 
 
 
 

A new developer is having continuing conflicts with existing Development Team members and creating a hostile environment. lf necessary, responsible for removing the team member?

 
 
 
 

When is the Sprint Backlog created?

 
 
 
 

If burndown charts are used to visualize progress, what does a trend line through a release burndown chart indicate?

 
 
 
 

When should a Sprint Goal be created?

 
 
 
 
 

Why does a Development Team need a Sprint Goal?

 
 
 
 

A Scrum Master is introducing Scrum a new Development Team. The Development Team has decided that a retrospective is unnecessary. What action should the Scrum Master take?

 
 
 
 

What are two ways that architecture and infrastucture are handled in Scrum?
(Choose the best two answers)

 
 
 
 

For which is the Scrum Master responsible?

 
 
 
 

A Scrum Team is only allowed to meet with stakeholders during Sprint Review.

 
 

What are two responsibilities of testers in a Development Team?
(Choose two answers)

 
 
 
 
 

Which two things should the Development Team do during the first Sprint?
(Choose 2 answers)

 
 
 
 
 

Which of the following best describes an increment of working software?

 
 
 
 
 

Who is responsible for engaging the stakeholders?

 
 
 
 
 

Sprint burndown charts are an efficient tracking tool because they allow.

 
 
 
 

Scrum has a role called “Project Manager”

 
 

What happens if the Development Team cannot complete its work by the end of the Sprint?

 
 
 

Which topics should be discussed in the Sprint Review?
(Choose the best answer)

 
 
 
 

What are two good ways for the Development Team to make non-functional requirements visible?
(Choose the best two answers)

 
 
 
 

Which is NOT a Development Team responsibility?

 
 
 
 
 

Which technique is the least productive way the Scrum Master can ensure that the Development Team communicates effectively with the Product Owner?

 
 
 
 

What is the time-box the Sprint Planning meeting?

 
 
 
 

What does it mean to say that an event has a time-box?

 
 
 
 

Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?

 
 
 
 

Which three questions might be answered by Development Team members at the Daily Scrum?
(Choose the best three answers)

 
 
 
 
 
 
 

During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?

 
 
 
 

When is a Spring canceled?

 
 
 
 

How much time is required after a Sprint to prepare for the next Sprint?

 
 
 
 
 

When may a Development Team change its engineering practices?

 
 
 
 
 

When is implementation of a product backlog item considered complete?
(Choose the best answer)

 
 
 
 

Who should make sure everyone on the Development Team does his or her tasks for the Sprint?

 
 
 
 
 

Which two of the following are true about the Scrum Master role?
(Choose two answers)

 
 
 
 
 

Multiple Scrum Teams working on the same product or system all select work from the same Product Backlog

 
 

Who can abnormally terminate a Sprint?

 
 
 
 

Scrum is a methodology that tells how to build software incrementally.

 
 

Which are properties of the Daily Scrum?
(Choose 2 answers)

 
 
 
 
 
 

When many Scrum Teams are working on the same product, should all of their in increments be integrated every Sprint?

 
 
 
 

When is a Sprint over?

 
 
 
 

What is the primary way a Scrum Master keeps a Development Team working at its highest level of productivity?

 
 
 
 

Which of the following are true about the Product Owner role?
(Choose 3 answers)

 
 
 
 
 

During the Daily Scrum, the Scrum Master’s role is to:

 
 
 
 
 

Who should know the most about the progress toward a business objective or a release?

 
 
 
 

Which three of the following are true about Scrum?
(Choose three answers)

 
 
 
 
 

What happens if the Development Team cannot complete its work by the end of the Sprint?

 
 
 

What two factors are best considered when establishing the Sprint length?
(Choose the best two answers)

 
 
 
 
 

The Scrum Master observes the Product Owner struggling with ordering the Product Backlog. What would you consideran appropriate action for Scrum Master to take?

 
 
 
 
 

Which three of the following are feedbacks loops in Scrum?
(Choose three answers)

 
 
 
 
 

Which of the following is not a time-box in Scrum?

 
 
 
 
 
 
 

The Sprint Goal is a result of Sprint Planning, as is the Sprint Backlog

 
 

Several Sprints into a project, the Product Owner tells the Scrum Master that a key stakeholder just started using the product. The stakeholder is unhappy with the slow performance. What are two good options for the Scrum Master?
(Choose the best two answers)

 
 
 
 
 

Which three of the following are time-boxed events in Scrum?
(Choose the best three answers)

 
 
 
 
 
 
 

Multiple Scrum Teams working on the same project must have the same Sprint start date.

 
 

Product Owner makes sure the team selects enough from the Product Backlog for a Sprint to satisfy the stakeholders.

 
 

Who is responsable for tracking the remaining work of the Sprint?

 
 
 
 
 

Who determines how work is performed during the sprint?

 
 
 
 
 

The Product Backlog is ordered by:

 
 
 
 
 

Who creates the definition of “Done”?

 
 
 
 

How much of the Backlog must be defined during the Sprint Planning meeting?

 
 
 
 

Cross-functional teams are optimized to work on one technical layer of a system only (e.g. GUI, database, middle tier, interfaces)

 
 

Which two activities will a product Owner engage in during a Sprint?
(Choose 2 answers)

 
 
 
 
 

During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?

 
 
 
 

Upon What kind of process control is SCRUM based

 
 
 
 

When many Scrum Teams are working on the same product, should all of their in increments be integrated every Sprint?

 
 
 
 

Choose three responsibilities of a self-organizing Development Team.
(Choose three answers)

 
 
 
 
 
 

What is the maximum length of a Sprint?

 
 
 
 

How often should Development Team membership change?

 
 
 
 

Why does a Development Team need a Sprint Goal?

 
 
 
 

What is the purpose of a Sprint Review?

 
 
 
 

Which of these may a Development Team deliver at the end of a Sprint?

 
 
 
 

A Scrum Master is introducing Scrum a new Development Team. The Development Team has decided that a retrospective is unnecessary. What action should the Scrum Master take?

 
 
 
 